430.2 MW Natural Gas operating in Middlesex, NJ — PJM Interconnection, LLC
430.2 MW
Nameplate Capacity
3
Generators
units
Natural Gas Fired Combined Cycle
Technology
1991
Operating Since
Coordinates
40.4390, -74.3444
County
Middlesex, NJ
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Sayreville Power Generation LP | Vistra | NextEra Energy Resources |
| Owner(s) | Vistra Corp | Vistra | — |
| Status | Operating | — | — |
The Sayreville Energy Center, or Sayreville Cogen Facility, is a combined cycle power station in Sayreville, New Jersey owned in part and operated by NextEra Energy Resources. Built by Westinghouse, it opened in 1991. It provides power to the PJM Interconnection and the Long Island Power Authority.
Read more on WikipediaThe Sayreville Cogeneration Facility is a 430.2 MW natural gas-fired combined cycle power plant located in Middlesex County, New Jersey. The plant began operating in 1991 and is owned by Vistra. The operator listed with the EIA is Sayreville Power Generation LP. The facility consists of three generators.
In the most recent year with available data, the plant generated 534,828 MWh of electricity, resulting in a capacity factor of 14.1%. The Sayreville Cogeneration Facility operates within the PJM Interconnection, LLC balancing authority and the RFC NERC region. It is ranked as the 12th largest power plant out of 19 in New Jersey, and 528th out of 945 nationally.
Generated from EIA, GEM, and public data sources
ISO/RTO
PJM
Market
ISO/RTO Member
NERC Region
RFC
Balancing Authority
PJM Interconnection, LLC (PJM)
Grid Voltage
230.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
9.5K MWh
Latest Month
534.8K MWh
Annual Generation
14.1%
Capacity Factor
CO₂ Intensity
1031 lb/MWh
NOx
0.721 lb/MWh
SO₂
0.005 lb/MWh
CH₄
0.019 lb/MWh
N₂O
0.002 lb/MWh
Capacity Factor
24.9%
Annual Net Gen
938 GWh
CO₂eq
1032 lb/MWh
Subregion
RFC East
2013
$965/kW
Est. Construction Cost
Total estimated cost: $415.2M
Point of Interconnection
Nearest Substation
South River Substation · 230 kV
Substation Distance
< 10 km
Operator
Jersey Central Power and Light
Coord Source
OSM spatial
Market Position
ISO/RTO Market
PJM
LMP Node
50726
Pricing Hub
WESTERN HUB
Node Source
EIA-860 direct report
No news articles linked yet for this plant.
News enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No ask pi reports yet for this entity.
ask pi about Sayreville Cogeneration Facility