Search plants, projects, owners, and states
1.5 MW Hydro operating in Lewis, NY — New York Independent System Operator
1.5 MW
Nameplate Capacity
1
Generators
unit
Conventional Hydroelectric
Technology
1985
Operating Since
Coordinates
43.8836, -75.4281
County
Lewis, NY
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Eagle Creek Renewable Energy, LLC | — | — |
| Owner(s) | Eagle Creek Beaver Falls, LLC | — | — |
| Status | Operating | — | — |
The Upper Beaver Falls Project is a 1.5 MW hydroelectric power plant located in Lewis County, New York. The plant began operating in 1985 and has one generator utilizing conventional hydroelectric technology. The primary fuel source is water (WAT). Eagle Creek Renewable Energy, LLC is the plant's operator.
The Upper Beaver Falls Project operates within the New York Independent System Operator (NYISO) balancing authority and the Northeast Power Coordinating Council (NPCC) NERC region. In terms of size, the plant ranks 146th out of 165 power plants in New York state, and 1307th out of 1464 plants nationally. The plant's latest annual generation was 6,039 MWh, resulting in a capacity factor of 45.8%.
Generated from EIA, GEM, and public data sources
ISO/RTO
NYISO
Market
ISO/RTO Member
NERC Region
NPCC — Northeast Power Coordinating Council
Balancing Authority
333 MWh
Latest Month
6.0K MWh
Annual Generation
45.8%
Capacity Factor
2013
$2,294/kW
Est. Construction Cost
Total estimated cost: $3.4M
Market Position
ISO/RTO Market
NYISO
LMP Node
23633
Pricing Hub
NYISO Zone E
Node Source
EIA-860 direct report
No news articles linked yet for this plant.
News enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No ask pi reports yet for this entity.
ask pi about Upper Beaver Falls ProjectNew York Independent System Operator (NYIS)
Grid Voltage
23.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP