Search plants, projects, owners, and states
90 MW Geothermal operating in Inyo, CA — California Independent System Operator
90 MW
Nameplate Capacity
3
Generators
units
Geothermal
Technology
1988
Operating Since
Coordinates
36.0019, -117.7886
County
Inyo, CA
Nearby Plants
Owner data does not fully agree across sources.
EIA typically reports the operating utility, while GEM resolves to the financial owner or parent corporation. Both can be correct.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Coso Operating Co LLC | Coso Operating | — |
| Owner(s) | Coso Operating Co LLC | Atlantica Sustainable Infrastructure | — |
| Status | Operating | operating | — |
Coso Energy Developers is a 90 MW geothermal power plant located in Inyo County, California. The plant began operating in 1988 and consists of 3 generators utilizing geothermal technology. It is owned by Atlantica Sustainable Infrastructure, a company based in the United Kingdom, and operated by Coso Operating Co LLC. The plant is interconnected to the California Independent System Operator (CAISO) balancing authority within the Western Electricity Coordinating Council (WECC) NERC region.
In the most recent year with available data, Coso Energy Developers generated 244,200 MWh of electricity, achieving a capacity factor of 30.9%. The plant is a significant geothermal energy producer in California, ranking 8th out of 33 geothermal plants in the state and 11th out of 70 nationally.
Generated from EIA, GEM, and public data sources
ISO/RTO
CAISO
Market
ISO/RTO Member
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
California Independent System Operator (CISO)
Grid Voltage
230.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP
19.4K MWh
Latest Month
244.2K MWh
Annual Generation
30.9%
Capacity Factor
CO₂ Intensity
89 lb/MWh
NOx
0.001 lb/MWh
SO₂
0.000 lb/MWh
CH₄
—
N₂O
—
Capacity Factor
35.2%
Annual Net Gen
277 GWh
CO₂eq
89 lb/MWh
Subregion
WECC California
2013
$2,851/kW
Est. Construction Cost
Total estimated cost: $256.6M
Market Position
ISO/RTO Market
CAISO
LMP Node
BLME8G_7_B1
Pricing Hub
TH_ZP26_GEN-APND
Location Type
Pricing Node
Node Source
Curated node match
Last updated 2026-03-26