30.4 MW Natural Gas operating in Davis, UT — PacifiCorp - East
30.4 MW
Nameplate Capacity
3
Generators
units
Natural Gas Fired Combustion Turbine
Technology
2001
Operating Since
Coordinates
40.8868, -111.8851
County
Davis, UT
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | City of Bountiful - (UT) | — | — |
| Owner(s) | City of Bountiful | — | — |
| Status | Operating | — | — |
The Bountiful City power plant is located in Davis County, Utah. It is owned and operated by the City of Bountiful. The plant has a total capacity of 30.4 MW consisting of three natural gas-fired combustion turbine generators. Commercial operation began in 2001. The plant operates within the PacifiCorp - East balancing authority, which is part of the Western Electricity Coordinating Council (WECC) NERC region.
In the most recent year with available data, the plant generated 28,385 MWh of electricity, achieving a capacity factor of 10.6%. Bountiful City ranks as the 10th largest power plant in Utah out of 24 facilities, and it holds a national ranking of 1234 out of 1963 plants.
Generated from EIA, GEM, and public data sources
Grid Region
Mountain West
Market
WEIM Participant
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
2.5K MWh
Latest Month
28.4K MWh
Annual Generation
10.6%
Capacity Factor
CO₂ Intensity
1333 lb/MWh
NOx
4 lb/MWh
SO₂
2013
$965/kW
Est. Construction Cost
Total estimated cost: $29.3M
This plant's balancing authority participates in CAISO's Western Energy Imbalance Market (WEIM). Direct nodal pricing data is not yet available.
Last updated 2026-03-14
View all articlesNo ask pi reports yet for this entity.
ask pi about Bountiful CityPacifiCorp - East (PACE)
Grid Voltage
46.0 kV
Regulatory Status
RE — Regulated
Entity Type
Municipal
Sector
Electric Utility
0.036 lb/MWh
CH₄
0.025 lb/MWh
N₂O
0.003 lb/MWh
Capacity Factor
8.0%
Annual Net Gen
21 GWh
CO₂eq
1334 lb/MWh
Subregion
WECC Northwest