23.4 MW Conventional Hydroelectric (3 MW) + Wood/Wood Waste Biomass (20 MW) operating in Marathon, WI — Midcontinent Independent Transmission System Operator, Inc..
23.4 MW
Nameplate Capacity
5
Generators
units
Hybrid (2)
Technology
Conventional Hydroelectric + Wood/Wood Waste Biomass
1916
Operating Since
Coordinates
44.7881, -89.6917
County
Marathon, WI
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Ahlstrom-Munksjo NA Specialty Solutions, LLC | Ahlstrom-Munksjo NA Specialty Solutions LLC | — |
| Owner(s) | Ahlstrom-Munksjo NA Specialty Solutions, LLC | Bain Capital | — |
| Status | Operating | operating | — |
The Mosinee Mill is a hybrid power plant located in Marathon County, Wisconsin. It has a total capacity of 23.4 MW across 5 generators, utilizing both conventional hydroelectric and wood/wood waste biomass technologies. The plant began operating in 1916 and is owned by Bain Capital, with Ahlstrom-Munksjo NA Specialty Solutions, LLC as the listed operator per EIA data. The primary fuel source is listed as WAT (waste).
The plant operates within the Midcontinent Independent Transmission System Operator, Inc. (MISO) balancing authority and the MRO NERC region. In the most recent year with available data, the Mosinee Mill generated 117,962 MWh, achieving a capacity factor of 57.6%. The plant is ranked 7th out of 65 power plants in Wisconsin and 456th out of 1464 nationally.
Generated from EIA, GEM, and public data sources
ISO/RTO
MISO
Market
ISO/RTO Member
NERC Region
MRO — Midwest Reliability Organization
Balancing Authority
Midcontinent Independent Transmission System Operator, Inc.. (MISO)
Grid Voltage
46.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Industrial
Sector
Industrial CHP
11.2K MWh
Latest Month
118.0K MWh
Annual Generation
57.6%
Capacity Factor
CO₂ Intensity
530 lb/MWh
NOx
2 lb/MWh
SO₂
6 lb/MWh
CH₄
0.091 lb/MWh
N₂O
0.023 lb/MWh
Capacity Factor
58.1%
Annual Net Gen
119 GWh
CO₂eq
538 lb/MWh
Subregion
MRO East
2013
$3,495/kW
Est. Construction Cost
Total estimated cost: $81.8M
Market Position
ISO/RTO Market
MISO
LMP Node
—
Pricing Hub
MICHIGAN.HUB
Alt. Hub / Zone
MINN.HUB
Node Source
OSM spatial match
Last updated 2026-03-26
View all 7 articlesNo ask pi reports yet for this entity.
ask pi about Mosinee Mill