3.6 MW Hydro operating in Butte, ID — PacifiCorp - East
3.6 MW
Nameplate Capacity
1
Generators
unit
Conventional Hydroelectric
Technology
1987
Operating Since
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Dry Creek LLC | — | — |
| Owner(s) | Dry Creek LLC | — | — |
| Status | Operating | — | — |
The Dry Creek Project is a 3.6 MW conventional hydroelectric power plant located in Butte County, Idaho. The plant began operating in 1987 and has one generator. It is owned and operated by Dry Creek LLC. The plant's output is managed by the PacifiCorp - East balancing authority within the Western Electricity Coordinating Council (WECC) NERC region.
In the most recent year of data, the Dry Creek Project generated 10,094 MWh of electricity, achieving a capacity factor of 31.9%. The plant ranks 48th out of 76 power plants in Idaho based on capacity, and 994th out of 1464 plants nationally.
Generated from EIA, GEM, and public data sources
Grid Region
Mountain West
Market
WEIM Participant
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
473 MWh
Latest Month
10.1K MWh
Annual Generation
31.9%
Capacity Factor
2013
$2,294/kW
Est. Construction Cost
Total estimated cost: $8.3M
This plant's balancing authority participates in CAISO's Western Energy Imbalance Market (WEIM). Direct nodal pricing data is not yet available.
No news articles linked yet for this plant.
News enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No ask pi reports yet for this entity.
ask pi about Dry Creek ProjectPacifiCorp - East (PACE)
Grid Voltage
25.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP