Search plants, projects, owners, and states
1 MW Solar operating in Riverside, CA — California Independent System Operator
1 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2008
Operating Since
Coordinates
33.5634, -114.9192
County
Riverside, CA
Nearby Plants
Owner data does not fully agree across sources.
EIA typically reports the operating utility, while GEM resolves to the financial owner or parent corporation. Both can be correct.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | SunE CPA CDC2 LLC | SunE CPA CDC2 | — |
| Owner(s) | SunE CPA CDC2 LLC | WF-SE-1 Solar Statutory Trust | — |
| Status | Operating | operating | — |
GEM identifies the owner as WF-SE-1 Solar Statutory Trust
This entity is not yet in the GEM ownership database — chain unavailable.
The SunEdison Ironwood State Prison solar photovoltaic plant is located in Riverside County, California. The plant has a total capacity of 1 MW and consists of a single generator. It began operating in 2008 and is owned and operated by SunE CPA CDC2 LLC. The plant utilizes single-axis tracking to maximize solar energy capture.
In the most recent year with available data, the plant generated 996 MWh of electricity, resulting in a capacity factor of 11.4%. The plant operates within the California Independent System Operator (CAISO) balancing authority and the Western Electricity Coordinating Council (WECC) NERC region. Based on its generating capacity, the SunEdison Ironwood State Prison plant ranks 767th out of 862 power plants in California and 6340th out of 7108 plants nationally.
Generated from EIA, GEM, and public data sources
ISO/RTO
CAISO
Market
ISO/RTO Member
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
71 MWh
Latest Month
996 MWh
Annual Generation
11.4%
Capacity Factor
2013
$3,757/kW
Est. Construction Cost
Total estimated cost: $3.8M
Point of Interconnection
Nearest Substation
Colorado River Substation · 500 kV
Substation Distance
< 10 km
Operator
Southern California Edison
Coord Source
OSM spatial
Market Position
ISO/RTO Market
CAISO
LMP Node
—
Pricing Hub
TH_SP15_GEN-APND
Node Source
OSM spatial match
Substation identified. Node ID not yet resolved against ISO roster.
No news articles linked yet for this plant.
News enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No ask pi reports yet for this entity.
ask pi about SunEdison Ironwood State PrisonCalifornia Independent System Operator (CISO)
Grid Voltage
12.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP