3.5 MW Solar operating in Polk, FL — Tampa Electric Company
3.5 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2012
Operating Since
Coordinates
27.9917, -82.0453
County
Polk, FL
Nearby Plants
Owner data does not fully agree across sources.
EIA typically reports the operating utility, while GEM resolves to the financial owner or parent corporation. Both can be correct.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Sun E N7 Holdings LLC | NVT LICENSES | — |
| Owner(s) | Sun E N7 Holdings LLC | SE Solar Trust VII | — |
| Status | Operating | operating | — |
GEM identifies the owner as SE Solar Trust VII
This entity is not yet in the GEM ownership database — chain unavailable.
The Lakeland Electric Co. - Airport II solar photovoltaic plant is located in Polk County, Florida. The plant has a total capacity of 3.5 MW and consists of a single generator. It commenced operations in 2012 and is owned/operated by Sun E N7 Holdings LLC. The plant utilizes single-axis solar tracking technology.
In the most recent year with available data, the plant generated 2,228 MWh of electricity, resulting in a capacity factor of 7.2%. The Airport II plant operates within the balancing authority of Tampa Electric Company and is located within the SERC NERC region. It is ranked as the 206th largest power plant in Florida out of 227 plants, and 3666th nationally out of 7108 plants. The plant's primary fuel source is solar.
Generated from EIA, GEM, and public data sources
Grid Region
Southeast
Market
SEEM Participant
NERC Region
SERC — SERC Reliability Corporation
Balancing Authority
138 MWh
Latest Month
2.2K MWh
Annual Generation
7.2%
Capacity Factor
Data from 2013–2024
$16.6/MWh
Energy Value
$22.6/MWh
Capacity Value
This plant's balancing authority participates in the Southeast Energy Exchange Market (SEEM). SEEM is a bilateral exchange — no public nodal pricing.
No news articles linked yet for this plant.
News enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No ask pi reports yet for this entity.
ask pi about Lakeland Electric Co. (FL) - Airport IITampa Electric Company (TEC)
Grid Voltage
1.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector