1.5 MW Natural Gas operating in Bristol, MA — ISO New England Inc.
1.5 MW
Nameplate Capacity
1
Generators
unit
Natural Gas Fired Combustion Turbine
Technology
2015
Operating Since
Coordinates
41.9318, -70.9584
County
Bristol, MA
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Massachusetts Department of Correction | — | — |
| Owner(s) | Commonwealth of Massachusetts | — | — |
| Status | Operating | — | — |
The Bridgewater Complex Co-Generation Plant is a 1.5 MW natural gas-fired power plant located in Bristol County, Massachusetts. The plant began operating in 2015 and is owned and operated by the Massachusetts Department of Correction. It consists of a single natural gas-fired combustion turbine generator.
The plant operates within the ISO New England Inc. balancing authority and the Northeast Power Coordinating Council (NPCC) NERC region. In the most recent year with available data, the plant generated 1,117 MWh of electricity, achieving a capacity factor of 8.5%. Bridgewater Complex ranks as the 36th largest power plant in Massachusetts out of 37 plants, and 1776th nationally out of 1963 plants.
Generated from EIA, GEM, and public data sources
ISO/RTO
ISO-NE
Market
ISO/RTO Member
NERC Region
NPCC — Northeast Power Coordinating Council
Balancing Authority
ISO New England Inc. (ISNE)
Grid Voltage
13.8 kV
Regulatory Status
NR — Non-Regulated
Entity Type
State
Sector
Commercial CHP
99 MWh
Latest Month
1.1K MWh
Annual Generation
8.5%
Capacity Factor
CO₂ Intensity
996 lb/MWh
NOx
3 lb/MWh
SO₂
0.027 lb/MWh
CH₄
0.019 lb/MWh
N₂O
0.002 lb/MWh
Capacity Factor
65.5%
Annual Net Gen
9 GWh
CO₂eq
997 lb/MWh
Subregion
NPCC New England
2015
$812/kW
Est. Construction Cost
Total estimated cost: $1.2M
Point of Interconnection
Nearest Substation
Middleboro Substation · 115 kV
Substation Distance
< 10 km
Operator
Middleboro Gas & Electric
Coord Source
OSM spatial
Market Position
ISO/RTO Market
ISO-NE
LMP Node
—
Pricing Hub
.H.INTERNAL_HUB
Node Source
OSM spatial match
Substation identified. Node ID not yet resolved against ISO roster.
No news articles linked yet for this plant.
News enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No ask pi reports yet for this entity.
ask pi about Bridgewater Complex Co-Generation Plant