Search plants, projects, owners, and states
263.2 MW Natural Gas Fired Combined Cycle (205 MW) + Natural Gas Fired Combustion Turbine (58 MW) operating in Eaton, MI — Midcontinent Independent Transmission System Operator, Inc..
263.2 MW
Nameplate Capacity
4
Generators
units
Hybrid (2)
Technology
Natural Gas Fired Combined Cycle + Natural Gas Fired Combustion Turbine
2022
Operating Since
Coordinates
42.6907, -84.6580
County
Eaton, MI
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Lansing Board of Water and Light | Lansing Board of Water and Light | — |
| Owner(s) | Lansing Board of Water and Light | Lansing Board of Water and Light | — |
| Status | Operating | — | — |
Delta Energy Park is a 263.2 MW natural gas-fired power plant located in Eaton County, Michigan. The plant, which began operating in 2022, is owned and operated by the Lansing Board of Water and Light. It utilizes both natural gas-fired combined cycle and natural gas-fired combustion turbine technologies, classifying it as a hybrid plant. Delta Energy Park is connected to the Midcontinent Independent Transmission System Operator, Inc. (MISO) balancing authority and resides within the ReliabilityFirst Corporation (RFC) NERC region.
The facility consists of four generators and achieved a capacity factor of 63.9% in its most recent year of operation. Its latest annual generation was 1,471,915 MWh. Delta Energy Park ranks as the 16th largest power plant out of 25 in Michigan, and 689th out of 945 nationally. The plant has been the subject of 10 news articles, with coverage focusing on industry and regulatory matters.
Generated from EIA, GEM, and public data sources
ISO/RTO
MISO
Market
ISO/RTO Member
NERC Region
RFC
Balancing Authority
Midcontinent Independent Transmission System Operator, Inc.. (MISO)
Grid Voltage
138.0 kV
Regulatory Status
RE — Regulated
Entity Type
Municipal
Sector
Electric Utility
133.2K MWh
Latest Month
1.5M MWh
Annual Generation
63.9%
Capacity Factor
CO₂ Intensity
931 lb/MWh
NOx
0.175 lb/MWh
SO₂
0.005 lb/MWh
CH₄
0.017 lb/MWh
N₂O
0.002 lb/MWh
Capacity Factor
40.4%
Annual Net Gen
932 GWh
CO₂eq
932 lb/MWh
Subregion
RFC Michigan
2022
$820/kW
Est. Construction Cost
Total estimated cost: $215.8M
Point of Interconnection
Nearest Substation
Delta Energy Park Substation · 138 kV
Substation Distance
< 10 km
Operator
Lansing Board of Water & Light
Coord Source
OSM spatial
Market Position
ISO/RTO Market
MISO
LMP Node
CONS.LANS
Pricing Hub
MICHIGAN.HUB
Location Type
Load Zone
Node Source
EIA-860 direct report
Last updated 2026-03-26
View all 6 articlesNo ask pi reports yet for this entity.
ask pi about Delta Energy Park