2 MW Solar operating in Cleveland, NC — Duke Energy Carolinas
2 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2018
Operating Since
Coordinates
35.2313, -81.5648
County
Cleveland, NC
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Cardinal Renewables | Alchemy Renewable Energy | — |
| Owner(s) | Cardinal Renewables | — | — |
| Status | Operating | operating | — |
The 232 Long Branch 29 Solar I, LLC is a 2 MW solar photovoltaic power plant located in Cleveland County, North Carolina. The plant began operating in 2018 and has one generator. Cardinal Renewables is the operator. The plant utilizes fixed-tilt solar tracking technology.
In its most recent year of operation, the plant generated 2,135 MWh of electricity, achieving a capacity factor of 12.2%. The plant's output is delivered within the Duke Energy Carolinas balancing authority, which is part of the SERC NERC region. The plant ranks 658th in size among North Carolina's 770 power plants, and 4728th nationally out of 7108 plants.
Generated from EIA, GEM, and public data sources
Grid Region
Southeast
Market
SEEM Participant
NERC Region
SERC — SERC Reliability Corporation
Balancing Authority
116 MWh
Latest Month
2.1K MWh
Annual Generation
12.2%
Capacity Factor
Data from 2019–2024
$23.2/MWh
Energy Value
$22.3/MWh
Capacity Value
This plant's balancing authority participates in the Southeast Energy Exchange Market (SEEM). SEEM is a bilateral exchange — no public nodal pricing.
No news articles linked yet for this plant.
News enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No ask pi reports yet for this entity.
ask pi about 232 Long Branch 29 Solar I, LLCDuke Energy Carolinas (DUK)
Grid Voltage
12.47 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector