Search plants, projects, owners, and states
4.6 MW Solar operating in Maricopa, AZ — Salt River Project
4.6 MW
Nameplate Capacity
2
Generators
units
Solar Photovoltaic
Technology
2020
Operating Since
Coordinates
33.3473, -111.6022
County
Maricopa, AZ
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Apple, Inc | Apple | — |
| Owner(s) | Apple, Inc | — | — |
| Status | Operating | operating | — |
Mesa Carport PV is a 4.6 MW solar photovoltaic power plant located in Maricopa County, Arizona. The plant began operating in 2020 and is owned and operated by Apple, Inc. It utilizes two solar generators with fixed-tilt tracking. The plant's primary fuel source is solar energy.
In its most recent year of operation, Mesa Carport PV generated 5,923 MWh of electricity, achieving a capacity factor of 14.7%. The plant operates within the Salt River Project balancing authority and the Western Electricity Coordinating Council (WECC) NERC region. Mesa Carport PV ranks as the 57th largest solar plant in Arizona out of 93, and 3241st nationally out of 7108.
Generated from EIA, GEM, and public data sources
Grid Region
Mountain West
Market
WEIM Participant
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
0 MWh
Latest Month
5.9K MWh
Annual Generation
14.7%
Capacity Factor
Data from 2021–2024
$14.3/MWh
Energy Value
$21.9/MWh
Capacity Value
This plant's balancing authority participates in CAISO's Western Energy Imbalance Market (WEIM). Direct nodal pricing data is not yet available.
No news articles linked yet for this plant.
News enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No ask pi reports yet for this entity.
ask pi about Mesa Carport PVSalt River Project (SRP)
Grid Voltage
12.47 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Commercial
Sector
Commercial Non-CHP