200 MW Solar planned in Pueblo, CO — Western Area Power Administration - Rocky Mountain Region
200 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
Planned: —
Planned Operation
Coordinates
38.3821, -104.9141
County
Pueblo, CO
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | 174 Power Global Corp. | 174 Power Global | — |
| Owner(s) | 174 Power Global Corp. | 174 Power Global | — |
| Status | Planned | announced | — |
GEM identifies the owner as 174 Power Global
This entity is not yet in the GEM ownership database — chain unavailable.
The Turkey Creek Solar Project is a 200 MW solar photovoltaic power plant located in Pueblo County, Colorado. The plant, identified by plant ID 64744, utilizes fixed-tilt solar tracking technology. It consists of a single generator and is operated by 174 Power Global Corp. The primary fuel source for electricity generation is solar energy.
Turkey Creek Solar Project is within the Western Electricity Coordinating Council (WECC) NERC region and operates under the balancing authority of the Western Area Power Administration - Rocky Mountain Region. The plant is ranked as the 5th largest solar facility out of 14 in the state of Colorado, and nationally it is ranked 264th out of 639 solar plants.
Generated from EIA, GEM, and public data sources
Grid Region
Mountain West
Market
Bilateral Market
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
No generation data available for this plant.
2023
$1,544/kW
Est. Construction Cost
Total estimated cost: $308.8M
This plant is in a bilateral market territory without organized wholesale pricing. Nodal pricing data is not available.
Last updated 2026-03-14
View all 5 articlesWestern Area Power Administration - Rocky Mountain Region (WACM)
Grid Voltage
115.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector