310 MW Solar operating in Bosque, TX — Electric Reliability Council of Texas, Inc.
310 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2025
Operating Since
Coordinates
31.8200, -97.5175
County
Bosque, TX
Nearby Plants
Owner data does not fully agree across sources.
EIA typically reports the operating utility, while GEM resolves to the financial owner or parent corporation. Both can be correct.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | BT Hickerson Solar, LLC | NextEra Energy | — |
| Owner(s) | BT Hickerson Solar, LLC | NextEra Energy | — |
| Status | Operating | operating | — |
BT Hickerson Solar, LLC is a 310 MW solar photovoltaic power plant located in Bosque County, Texas. The plant, identified by the EIA plant code 66903, is owned and operated by BT Hickerson Solar, LLC, a subsidiary of NextEra Energy. The facility utilizes fixed-tilt solar tracking technology. It is interconnected to the Electric Reliability Council of Texas (ERCOT) grid, operating within the TRE NERC region.
The plant is ranked as the 37th largest solar facility in Texas out of 192, and 69th nationally out of 639. The facility consists of one generator. Its primary fuel source is solar energy.
Generated from EIA, GEM, and public data sources
ISO/RTO
ERCOT
Market
ISO/RTO Member
NERC Region
TRE — Texas Reliability Entity
Balancing Authority
39.4K MWh
Latest Month
—
Annual Generation
—
Capacity Factor
2023
$1,543/kW
Est. Construction Cost
Total estimated cost: $478.3M
Market Position
ISO/RTO Market
ERCOT
LMP Node
DILEOS_UNIT1
Pricing Hub
HB_NORTH
Alt. Hub / Zone
LZ_NORTH
Location Type
Resource Node
Node Source
Curated node match
Last updated 2026-04-19
View all articlesElectric Reliability Council of Texas, Inc. (ERCO)
Grid Voltage
345.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP