Search plants, projects, owners, and states
200 MW Solar planned in Las Animas, CO — Public Service Company of Colorado
200 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
Planned: —
Planned Operation
Coordinates
37.4546, -104.4887
County
Las Animas, CO
Nearby Plants
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Cypress Creek Renewables | Cypress Creek Renewables | — |
| Owner(s) | Cypress Creek Renewables | Cypress Creek Renewables | — |
| Status | Planned | pre-construction | — |
GEM identifies the owner as Cypress Creek Renewables
This entity is not yet in the GEM ownership database — chain unavailable.
Elk Run is a 200 MW solar photovoltaic power plant located in Las Animas County, Colorado. The plant, which utilizes fixed-tilt solar tracking technology, is operated by Cypress Creek Renewables. It consists of a single generator and uses solar energy as its primary fuel source. Elk Run is within the Public Service Company of Colorado balancing authority and the Western Electricity Coordinating Council (WECC) NERC region.
Elk Run is the 6th largest solar power plant in Colorado out of 14 plants, and ranks 265th nationally out of 639 solar plants.
Generated from EIA, GEM, and public data sources
Grid Region
Mountain West
Market
Bilateral Market
NERC Region
WECC — Western Electricity Coordinating Council
Balancing Authority
No generation data available for this plant.
2023
$1,544/kW
Est. Construction Cost
Total estimated cost: $308.8M
This plant is in a bilateral market territory without organized wholesale pricing. Nodal pricing data is not available.
Last updated 2026-03-26
View all 7 articlesPublic Service Company of Colorado (PSCO)
Grid Voltage
230.0 kV
Regulatory Status
NR — Non-Regulated
Entity Type
Independent Power Producer
Sector
IPP Non-CHP