Search plants, projects, owners, and states
1 MW Solar operating in Stearns, MN
1 MW
Nameplate Capacity
1
Generators
unit
Solar Photovoltaic
Technology
2025
Operating Since
Coordinates
45.3898, -94.7118
County
Stearns, MN
Nearby Plants
Owner data does not fully agree across sources.
EIA typically reports the operating utility, while GEM resolves to the financial owner or parent corporation. Both can be correct.
| Field | EIA | GEM | Wikidata |
|---|---|---|---|
| Operator | Standard Solar | Enel Green Power NA, Inc. | — |
| Owner(s) | Standard Solar | Paynesville Solar LLC | — |
| Status | Operating | operating | — |
GEM identifies the owner as Paynesville Solar LLC
This entity is not yet in the GEM ownership database — chain unavailable.
No description available for this plant.
ISO/RTO
MISO
Market
ISO/RTO Member
NERC Region
—
Balancing Authority
No generation data available for this plant.
2023
$1,606/kW
Est. Construction Cost
Total estimated cost: $1.6M
Point of Interconnection
Nearest Substation
Paynesville Substation · 230 kV
Substation Distance
< 10 km
Coord Source
OSM spatial
Market Position
ISO/RTO Market
MISO
LMP Node
—
Pricing Hub
MINN.HUB
Node Source
OSM spatial match
Substation identified. Node ID not yet resolved against ISO roster.
No news articles linked yet for this plant.
News enrichment runs on demand — we have the pipeline, we just haven't fetched coverage for this plant yet. Request a detailed re-run and we'll add it.
No ask pi reports yet for this entity.
ask pi about Enterprise MN - Ferche CSG—
Grid Voltage
—
Regulatory Status
—
Entity Type
Independent Power Producer
Sector
IPP Non-CHP