AEC-GI-103
460 MW generation in Creek, OK · In queue since July 2022 · Proposed COD January 2027
460 MW
Capacity
1
Components
Gas
3y 10m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2027-01-31
AEC-GI-103 is a proposed 460 MW gas-fired generation project located in Creek County, Oklahoma. The project is being developed by Associated Electric Cooperative, Incorporated (AEC). It consists of a single 460 MW gas-powered component.
The project is currently active in the Southwest Power Pool (SPP) interconnection queue, with an entry date of July 21, 2022. Its proposed commercial operation date is January 31, 2027, and the interconnection agreement has been executed. The point of interconnection is the Bristow 138 kV Bus.
Generated from interconnection queue and public data sources
State
OK
County
Creek
Grid Region
Southeast
Market
—
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Service Type
—
Point of Interconnection
Bristow 138 kV Bus
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- SPP South Hub
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.