AEC-GI-121
460 MW generation in Randolph, MO · In queue since May 2024 · Proposed COD April 2029
460 MW
Capacity
1
Components
Gas
2 years
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-04-30
AEC-GI-121 is a proposed 460 MW gas-fired generation project located in Randolph County, Missouri. The project is being developed by Associated Electric Cooperative, Incorporated (AEC). It consists of 460 MW of gas-fired capacity.
The project is currently active in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of May 1, 2024. The proposed commercial operation date is April 30, 2029. The project's interconnection agreement status is currently in the Facility Study phase. The point of interconnection is the Thomas Hill - McCredie 345 kV substation.
Generated from interconnection queue and public data sources
State
MO
County
Randolph
Grid Region
Southeast
Market
—
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Service Type
—
Point of Interconnection
Thomas Hill - McCredie 345 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- AECI
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project AEC-GI-121