AEC-GI-122
500 MW generation in Randolph, MO · In queue since May 2024 · Proposed COD December 2028
500 MW
Capacity
1
Components
Wind
2 years
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
AEC-GI-122 is a proposed 500 MW wind generation project in Randolph County, Missouri. The project is being developed by Associated Electric Cooperative, Incorporated (AEC). It consists of 500 MW of wind power capacity.
The project is currently active in the Associated Electric Cooperative (AEC) generation interconnection queue, with an entry date of May 20, 2024. The proposed commercial operation date is December 31, 2028. The project's interconnection status is currently in the Facility Study phase, and the point of interconnection is the McCredie 345 kV substation.
Generated from interconnection queue and public data sources
State
MO
County
Randolph
Grid Region
Southeast
Market
—
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Service Type
—
Point of Interconnection
McCredie 345 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- AECI
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.