AEC-GI-123
300 MW generation in Craig, OK · In queue since September 2024 · Proposed COD December 2027
300 MW
Capacity
1
Components
Wind
1y 8m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
AEC-GI-123 is a proposed 300 MW wind generation project located in Craig County, Oklahoma. The project is being developed by Associated Electric Cooperative, Incorporated (AEC). It consists of 300 MW of wind capacity.
The project is currently in the Southwest Power Pool (SPP) interconnection queue, with an entry date of September 3, 2024. Its proposed commercial operation date is December 31, 2027. The project's interconnection status is currently in the System Impact Study phase, and it intends to interconnect to the Sportsman-Blackberry 345 kV line.
Generated from interconnection queue and public data sources
State
OK
County
Craig
Grid Region
Southeast
Market
—
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Service Type
—
Point of Interconnection
Sportsman-Blackberry 345 kV line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- SPP South Hub
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.