AEC-GI-60
18 MW generation in Gentry, MO · In queue since April 2017
18 MW
Capacity
1
Components
Wind
9y 1m
In Queue
IA Executed
IA Status
Total Duration
9y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Commercial operation date not yet determined
AEC-GI-60 is a proposed wind energy project with a total capacity of 18 MW, located in Gentry County, Missouri. The project is being developed by Associated Electric Cooperative, Incorporated (AEC). It consists of 18 MW of wind generation.
The project is listed in the Associated Electric Cooperative (AEC) interconnection queue as of April 4, 2017, with interconnection to the Winslow 161 kV Substation. The project's interconnection agreement (IA) has been executed.
Generated from interconnection queue and public data sources
State
MO
County
Gentry
Grid Region
Southeast
Market
—
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Service Type
—
Point of Interconnection
Winslow 161 kV Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- AECI
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project AEC-GI-60