Project AEC-GI-61 — Project Summary

Queue ID
AEC-GI-61
Capacity
230 MW
Technology
Wind
Status
active
Location
Nodaway, MO
Region
Southeast
Developer
IA Status
IA Executed

AEC-GI-61

AEC-GI-61BetaActiveWindAECLBNL

230 MW generation in Nodaway, MO · In queue since May 2017 · Proposed COD December 2019

230 MW

Capacity

1

Components

Wind

9 years

In Queue

IA Executed

IA Status

COD target: 2019

Interconnection

Total Duration

2y 7m

Schedule

77 months past proposed COD

Construction75%
Queue EntryMay 3, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2019-12-31

About

AEC-GI-61 is a proposed wind generation project with a total capacity of 230 MW located in Nodaway County, Missouri. The project is being developed by Associated Electric Cooperative, Incorporated (AEC). It consists of 230 MW of wind power.

The project is listed in the Associated Electric Cooperative (AEC) generation interconnection queue as of May 3, 2017. Its proposed commercial operation date was December 31, 2019, and the interconnection agreement has been executed. The point of interconnection is the Maryville 161 kV substation.

Generated from interconnection queue and public data sources

Project Details

State

MO

County

Nodaway

Grid Region

Southeast

Market

Developer

Utility

Associated Electric Cooperative, Incorporated

Entity

AEC

Service Type

Point of Interconnection

Maryville 161 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
AECI
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.