AEC-GI-90
100 MW generation in Randolph, MO · In queue since July 2020 · Proposed COD June 2027
100 MW
Capacity
1
Components
Solar
5y 10m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
6y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-06-30
AEC-GI-90 is a proposed solar generation project with a total capacity of 100 MW, located in Randolph County, Missouri. The project is being developed by Associated Electric Cooperative, Incorporated (AEC). It consists of 100 MW of solar photovoltaic generation.
The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue with an entry date of July 24, 2020. The proposed commercial operation date is June 30, 2027, and the Interconnection Agreement (IA) has been executed. The point of interconnection (POI) is the Montgomery City 161 kV substation.
Generated from interconnection queue and public data sources
State
MO
County
Randolph
Grid Region
Southeast
Market
—
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Service Type
—
Point of Interconnection
Montgomery City 161 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- AECI
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project AEC-GI-90