AEC-GI-95
247 MW generation in Dade, MO · In queue since December 2020 · Proposed COD December 2026
247 MW
Capacity
1
Components
Wind
5y 5m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
6 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2026-12-30
AEC-GI-95 is a proposed wind generation project with a total capacity of 247 MW, located in Dade County, Missouri. The project is being developed by Associated Electric Cooperative, Incorporated (AEC). It consists of 247 MW of wind generation capacity.
The project is listed in the Associated Electric Cooperative (AEC) interconnection queue as of December 4, 2020, with a proposed commercial operation date of December 30, 2026. The interconnection agreement (IA) has been executed. The point of interconnection (POI) is the Jasper-Morgan 345 kV line.
Generated from interconnection queue and public data sources
State
MO
County
Dade
Grid Region
Southeast
Market
—
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Service Type
—
Point of Interconnection
Jasper-Morgan 345 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- AECI
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.