AEC-GI-96
97.5 MW generation in Lincoln, OK · In queue since October 2021 · Proposed COD December 2026
97.5 MW
Capacity
1
Components
Wind
4y 7m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2026-12-01
AEC-GI-96 is a proposed wind generation project with a total capacity of 97.5 MW. The project is located in Lincoln County, Oklahoma, within the Southeast region. It is being developed by Associated Electric Cooperative, Incorporated (AEC).
The project is listed in the Associated Electric Cooperative, Incorporated (AEC) interconnection queue with a queue entry date of October 22, 2021. The proposed commercial operation date is December 1, 2026, and the Interconnection Agreement (IA) has been executed. The point of interconnection (POI) is at the Stroud 138kV substation.
Generated from interconnection queue and public data sources
State
OK
County
Lincoln
Grid Region
Southeast
Market
—
Developer
—
Utility
Associated Electric Cooperative, Incorporated
Entity
AEC
Service Type
—
Point of Interconnection
Stroud 138kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- SPP South Hub
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project AEC-GI-96