APS-Q225
200 MW hybrid in Maricopa, AZ · In queue since September 2014 · Proposed COD December 2021
200 MW
Capacity
1
Components
Solar
11y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Total Duration
7y 3m
Schedule
53 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-22
APS-Q225 is a proposed 200 MW solar and battery hybrid project located in Maricopa County, Arizona. The development project consists of 200 MW of solar generation capacity. It is listed in the Arizona Public Service (APS) interconnection queue, with a queue entry date of September 25, 2014. The proposed commercial operation date is December 22, 2021.
The interconnection agreement (IA) status for APS-Q225 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Hoodoo Wash 500kV Substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Hoodoo Wash 500kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q225