APS-Q227
500 MW hybrid in Yuma, AZ · In queue since August 2015 · Proposed COD December 2021
500 MW
Capacity
1
Components
Solar
10y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Total Duration
6y 4m
Schedule
53 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-22
APS-Q227 is a proposed 500 MW hybrid solar and battery project located in Yuma County, Arizona. The project, which consists of 500 MW of solar power, is in the Arizona Public Service (APS) interconnection queue as of August 17, 2015. The proposed commercial operation date is December 22, 2021.
The interconnection agreement (IA) status for APS-Q227 is listed as "In Progress (unknown study)". The point of interconnection (POI) is Hoodoo Wash 500kV.
Generated from interconnection queue and public data sources
State
AZ
County
Yuma
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Hoodoo Wash 500kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.