APS-Q230
200 MW generation in Navajo, AZ · In queue since September 2015 · Proposed COD December 2021
200 MW
Capacity
1
Components
Solar
10y 8m
In Queue
IA Executed
IA Status
COD target: 2021
Total Duration
6y 3m
Schedule
53 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2021-12-24
APS-Q230 is a proposed 200 MW solar generation project located in Navajo County, Arizona. The project is interconnected to the Arizona Public Service (APS) system and entered the APS interconnection queue on September 30, 2015. The proposed commercial operation date was December 24, 2021, and the interconnection agreement has been executed.
The point of interconnection for the project is the Cholla 500kV Substation. The project consists of 200 MW of solar photovoltaic generation.
Generated from interconnection queue and public data sources
State
AZ
County
Navajo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Cholla 500kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q230