APS-Q252
250 MW hybrid in Yuma, AZ · In queue since March 2017 · Proposed COD December 2021
250 MW
Capacity
1
Components
Solar
9y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Total Duration
4y 9m
Schedule
53 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-31
APS-Q252 is a proposed 250 MW solar and battery hybrid project located in Yuma County, Arizona. The project, interconnected with Arizona Public Service (APS), entered the APS interconnection queue on March 29, 2017, with a proposed commercial operation date of December 31, 2021. The interconnection agreement is currently listed as "In Progress (unknown study)".
The development project consists of 250 MW of solar capacity. The interconnection point is the Hoodoo Wash 500kV Substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
AZ
County
Yuma
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Hoodoo Wash 500kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.