APS-Q254
100 MW generation in Pinal, AZ · In queue since March 2017 · Proposed COD October 2022
100 MW
Capacity
1
Components
Solar
9y 2m
In Queue
IA Executed
IA Status
COD target: 2022
Total Duration
5y 7m
Schedule
43 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2022-10-28
APS-Q254 is a proposed 100 MW solar generation project located in Pinal County, Arizona. The project is interconnected with Arizona Public Service (APS) and entered the APS interconnection queue on March 31, 2017. The proposed commercial operation date was October 28, 2022, and the Interconnection Agreement (IA) has been executed. The point of interconnection is the Thornton 69kV Substation.
The development project consists of 100 MW of solar photovoltaic generation. It is currently listed as an active project in the interconnection queue.
Generated from interconnection queue and public data sources
State
AZ
County
Pinal
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Thornton 69kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN