Project APS-Q256 — Project Summary

Queue ID
APS-Q256
Capacity
100 MW
Technology
Solar+Battery
Status
active
Location
Pinal, AZ
Region
West
Developer
IA Status
In Progress (unknown study)

APS-Q256

APS-Q256BetaActiveSolarBatteryAPSLBNL

100 MW hybrid in Pinal, AZ · In queue since May 2017 · Proposed COD January 2023

100 MW

Capacity

1

Components

Solar

9 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection

Total Duration

5y 8m

Schedule

40 months past proposed COD

In Study38%
Queue EntryMay 24, 2017

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-01-30

About

APS-Q256 is a proposed 100 MW hybrid solar and battery project located in Pinal County, Arizona. The development project consists of 100 MW of solar capacity. It is listed in the Arizona Public Service (APS) interconnection queue as APS-Q256, with a queue entry date of May 24, 2017. The proposed commercial operation date is January 30, 2023.

The interconnection status is listed as "In Progress (unknown study)". The point of interconnection is the Milligan 69kV Substation.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Pinal

Grid Region

Mountain West

Market

Developer

Utility

Arizona Public Service

Entity

APS

Service Type

Point of Interconnection

Milligan 69kV Substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project APS-Q256