APS-Q256
100 MW hybrid in Pinal, AZ · In queue since May 2017 · Proposed COD January 2023
100 MW
Capacity
1
Components
Solar
9 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
5y 8m
Schedule
40 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-01-30
APS-Q256 is a proposed 100 MW hybrid solar and battery project located in Pinal County, Arizona. The development project consists of 100 MW of solar capacity. It is listed in the Arizona Public Service (APS) interconnection queue as APS-Q256, with a queue entry date of May 24, 2017. The proposed commercial operation date is January 30, 2023.
The interconnection status is listed as "In Progress (unknown study)". The point of interconnection is the Milligan 69kV Substation.
Generated from interconnection queue and public data sources
State
AZ
County
Pinal
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Milligan 69kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q256