APS-Q259
400 MW hybrid in San Juan, NM · In queue since September 2017 · Proposed COD December 2021
400 MW
Capacity
1
Components
Solar
8y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Total Duration
4y 3m
Schedule
53 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-31
APS-Q259 is a proposed 400 MW hybrid solar and battery project located in San Juan County, New Mexico. The project, under development by Arizona Public Service (APS), consists of 400 MW of solar capacity. It is currently listed as active in the Arizona Public Service interconnection queue, with an original queue entry date of September 27, 2017.
The proposed commercial operation date (COD) for APS-Q259 is December 31, 2021. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Four Corners 345kV SY.
Generated from interconnection queue and public data sources
State
NM
County
San Juan
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Four Corners 345kV SY
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.