APS-Q264
130 MW hybrid in Pinal, AZ · In queue since September 2017 · Proposed COD December 2021
130 MW
Capacity
1
Components
Solar
8y 8m
In Queue
IA Executed
IA Status
COD target: 2021
Total Duration
4y 3m
Schedule
53 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2021-12-22
APS-Q264 is a proposed 130 MW hybrid solar and battery project located in Pinal County, Arizona. The project consists of 130 MW of solar generation. It is listed in the Arizona Public Service (APS) interconnection queue as entry APS-Q264, with a queue entry date of September 29, 2017. The proposed commercial operation date is December 22, 2021, and the interconnection agreement has been executed.
The project is interconnected to the Milligan Substation at 230kV. The developer is listed as APS. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
AZ
County
Pinal
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Milligan Substation 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN