APS-Q268
75 MW storage in Maricopa, AZ · In queue since March 2018 · Proposed COD December 2020
75 MW
Capacity
1
Components
Battery
8y 2m
In Queue
Construction
IA Status
COD target: 2020
Total Duration
2y 9m
Schedule
66 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2020-12-01
APS-Q268 is a proposed 75 MW battery storage project located in Maricopa County, Arizona. The project is listed in the Arizona Public Service (APS) interconnection queue, with an entry date of March 29, 2018. The proposed commercial operation date is December 1, 2020.
The project's interconnection status is listed as "Construction". The point of interconnection is the Sarival 69kV Substation.
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Sarival 69kV Sub
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q268