APS-Q269
450 MW storage in Maricopa, AZ · In queue since March 2018 · Proposed COD December 2022
450 MW
Capacity
1
Components
Battery
8y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
4y 9m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-16
APS-Q269 is a proposed 450 MW battery storage project located in Maricopa County, Arizona. The project is listed in the Arizona Public Service (APS) interconnection queue, with a queue entry date of March 29, 2018. The proposed commercial operation date is December 16, 2022.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is the Delaney 500kV substation.
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Delaney 500kV SY
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.