APS-Q273
477 MW generation in Navajo, AZ · In queue since March 2018 · Proposed COD December 2021
477 MW
Capacity
1
Components
Wind
8y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Total Duration
3y 9m
Schedule
53 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-21
APS-Q273 is a proposed wind generation project with a total capacity of 477 MW, located in Navajo County, Arizona. The project is listed in the Arizona Public Service (APS) interconnection queue, with a queue entry date of March 30, 2018. The proposed commercial operation date is December 21, 2021.
The interconnection agreement (IA) status for APS-Q273 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Preacher Canyon - Cholla 345kV substation.
Generated from interconnection queue and public data sources
State
AZ
County
Navajo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Preacher Canyon -Cholla 345kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.