Project APS-Q273 — Project Summary

Queue ID
APS-Q273
Capacity
477 MW
Technology
Wind
Status
active
Location
Navajo, AZ
Region
West
Developer
IA Status
In Progress (unknown study)

APS-Q273

APS-Q273BetaActiveWindAPSLBNL

477 MW generation in Navajo, AZ · In queue since March 2018 · Proposed COD December 2021

477 MW

Capacity

1

Components

Wind

8y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2021

Interconnection

Total Duration

3y 9m

Schedule

53 months past proposed COD

In Study38%
Queue EntryMar 30, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-12-21

About

APS-Q273 is a proposed wind generation project with a total capacity of 477 MW, located in Navajo County, Arizona. The project is listed in the Arizona Public Service (APS) interconnection queue, with a queue entry date of March 30, 2018. The proposed commercial operation date is December 21, 2021.

The interconnection agreement (IA) status for APS-Q273 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Preacher Canyon - Cholla 345kV substation.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Navajo

Grid Region

Mountain West

Market

Developer

Utility

Arizona Public Service

Entity

APS

Service Type

Point of Interconnection

Preacher Canyon -Cholla 345kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project APS-Q273