Project APS-Q274 — Project Summary

Queue ID
APS-Q274
Capacity
1000 MW
Technology
Solar
Status
active
Location
Coconino, AZ
Region
West
Developer
IA Status
IA Executed

APS-Q274

APS-Q274BetaActiveSolarAPSLBNL

1,000 MW generation in Coconino, AZ · In queue since March 2018 · Proposed COD December 2024

1,000 MW

Capacity

1

Components

Solar

8y 2m

In Queue

IA Executed

IA Status

COD target: 2024

Interconnection

Total Duration

6y 9m

Schedule

16 months past proposed COD

Construction75%
Queue EntryMar 30, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2024-12-31

About

APS-Q274 is a proposed 1000 MW solar generation project located in Coconino County, Arizona. The project, under development by Arizona Public Service (APS), consists of 1000 MW of solar photovoltaic generation. It is interconnected to the Arizona Public Service system at the Cedar Mountain - Moenkopi 500 kV Line.

The project is listed in the Arizona Public Service interconnection queue as entry APS-Q274, with an original queue entry date of March 30, 2018. The proposed commercial operation date is December 31, 2024, and the Interconnection Agreement (IA) has been executed.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Coconino

Grid Region

Mountain West

Market

Developer

Utility

Arizona Public Service

Entity

APS

Service Type

Point of Interconnection

Cedar Mountain - Moenkopi 500 kV Line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.