Project APS-Q276 — Project Summary

Queue ID
APS-Q276
Capacity
150 MW
Technology
Solar
Status
active
Location
Maricopa, AZ
Region
West
Developer
IA Status
In Progress (unknown study)

APS-Q276

APS-Q276BetaActiveSolarAPSLBNL

150 MW generation in Maricopa, AZ · In queue since March 2018 · Proposed COD April 2022

150 MW

Capacity

1

Components

Solar

8y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection

Total Duration

4y 1m

Schedule

50 months past proposed COD

In Study38%
Queue EntryMar 30, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-04-01

About

APS-Q276 is a proposed solar generation project with a total capacity of 150 MW, located in Maricopa County, Arizona. The project is in the Arizona Public Service (APS) interconnection queue, with a queue entry date of March 30, 2018. The proposed commercial operation date is April 1, 2022.

The interconnection agreement (IA) status for APS-Q276 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Delaney 500kV SY. The developer is listed as APS.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Maricopa

Grid Region

Mountain West

Market

Developer

Utility

Arizona Public Service

Entity

APS

Service Type

Point of Interconnection

Delaney 500kV SY

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project APS-Q276