APS-Q276
150 MW generation in Maricopa, AZ · In queue since March 2018 · Proposed COD April 2022
150 MW
Capacity
1
Components
Solar
8y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
4y 1m
Schedule
50 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-04-01
APS-Q276 is a proposed solar generation project with a total capacity of 150 MW, located in Maricopa County, Arizona. The project is in the Arizona Public Service (APS) interconnection queue, with a queue entry date of March 30, 2018. The proposed commercial operation date is April 1, 2022.
The interconnection agreement (IA) status for APS-Q276 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Delaney 500kV SY. The developer is listed as APS.
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Delaney 500kV SY
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q276