APS-Q295
250 MW hybrid in Pinal, AZ · In queue since March 2019 · Proposed COD December 2022
250 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Status
COD target: 2022
Total Duration
3y 9m
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2022-12-01
APS-Q295 is a proposed 250 MW hybrid solar and battery project located in Pinal County, Arizona. The project consists of 250 MW of solar generation. It is listed in the Arizona Public Service (APS) interconnection queue as of March 27, 2019, with a proposed commercial operation date of December 1, 2022. The project's interconnection agreement has been executed.
The project is interconnected to the Milligan 230kV Substation.
Generated from interconnection queue and public data sources
State
AZ
County
Pinal
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Milligan 230kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q295