APS-Q311
500 MW hybrid in Navajo, AZ · In queue since September 2019 · Proposed COD December 2021
500 MW
Capacity
1
Components
Wind
6y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Total Duration
2y 3m
Schedule
53 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-12-31
APS-Q311 is a proposed 500 MW hybrid wind and battery project located in Navajo County, Arizona. The project, which appeared in the Arizona Public Service (APS) interconnection queue on September 26, 2019, consists of 500 MW of wind generation capacity. The proposed commercial operation date is December 31, 2021.
The project's interconnection to the grid at the Sitgreaves substation is currently listed as "In Progress (unknown study)". The utility is Arizona Public Service (APS).
Generated from interconnection queue and public data sources
State
AZ
County
Navajo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Sitgreaves substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q311