APS-Q313
95 MW hybrid in Yavapai, AZ · In queue since September 2019 · Proposed COD December 2022
95 MW
Capacity
1
Components
Solar
6y 8m
In Queue
IA Executed
IA Status
COD target: 2022
Total Duration
3y 3m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2022-12-31
APS-Q313 is a proposed 95 MW hybrid solar and battery project located in Yavapai County, Arizona. The development project consists of 95 MW of solar capacity. It is interconnected to the Arizona Public Service (APS) grid at the Lonesome Valley 69kV point of interconnection.
The project is listed in the APS interconnection queue as of September 27, 2019, with a proposed commercial operation date of December 31, 2022. The interconnection agreement (IA) for the project has been executed.
Generated from interconnection queue and public data sources
State
AZ
County
Yavapai
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Lonesome Valley 69kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN