APS-Q314
300 MW storage in Maricopa, AZ · In queue since September 2019 · Proposed COD December 2022
300 MW
Capacity
1
Components
Battery
6y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
3y 3m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-16
APS-Q314 is a proposed 300 MW battery storage project located in Maricopa County, Arizona. The project is listed in the Arizona Public Service (APS) interconnection queue, with a queue entry date of September 30, 2019. The proposed commercial operation date is December 16, 2022. The interconnection agreement status is listed as "In Progress (unknown study)".
The development project is located in the West region and consists entirely of battery storage. The point of interconnection is the Scatter Wash 230kV substation. Recent news coverage has discussed the project.
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Scatter Wash 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q314