APS-Q315
50 MW storage in Coconino, AZ · In queue since September 2019 · Proposed COD October 2022
50 MW
Capacity
1
Components
Battery
6y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
3y 1m
Schedule
43 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-10-31
APS-Q315 is a proposed 50 MW battery storage project located in Coconino County, Arizona. The project is listed in the Arizona Public Service (APS) interconnection queue, with a queue entry date of September 30, 2019. The proposed commercial operation date is October 31, 2022.
The interconnection agreement for the project is currently listed as "In Progress" with an unknown study. The point of interconnection is the Woody Mountain 69kV substation.
Generated from interconnection queue and public data sources
State
AZ
County
Coconino
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Woody Mountain 69kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.