Project APS-Q315 — Project Summary

Queue ID
APS-Q315
Capacity
50 MW
Technology
Battery
Status
active
Location
Coconino, AZ
Region
West
Developer
IA Status
In Progress (unknown study)

APS-Q315

APS-Q315BetaActiveBatteryAPSLBNL

50 MW storage in Coconino, AZ · In queue since September 2019 · Proposed COD October 2022

50 MW

Capacity

1

Components

Battery

6y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2022

Interconnection

Total Duration

3y 1m

Schedule

43 months past proposed COD

In Study38%
Queue EntrySep 30, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-10-31

About

APS-Q315 is a proposed 50 MW battery storage project located in Coconino County, Arizona. The project is listed in the Arizona Public Service (APS) interconnection queue, with a queue entry date of September 30, 2019. The proposed commercial operation date is October 31, 2022.

The interconnection agreement for the project is currently listed as "In Progress" with an unknown study. The point of interconnection is the Woody Mountain 69kV substation.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Coconino

Grid Region

Mountain West

Market

Developer

Utility

Arizona Public Service

Entity

APS

Service Type

Point of Interconnection

Woody Mountain 69kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project APS-Q315