Project APS-Q317 — Project Summary

Queue ID
APS-Q317
Capacity
750 MW
Technology
Solar+Battery
Status
active
Location
Coconino, AZ
Region
West
Developer
IA Status
Cluster Study

APS-Q317

APS-Q317BetaActiveSolarBatteryAPSLBNL

750 MW hybrid in Coconino, AZ · In queue since September 2019 · Proposed COD June 2023

750 MW

Capacity

1

Components

Solar

6y 8m

In Queue

Cluster Study

IA Status

COD target: 2023

Interconnection

Total Duration

3y 9m

Schedule

35 months past proposed COD

Impact Study25%
Queue EntrySep 30, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-06-30

About

APS-Q317 is a proposed 750 MW hybrid solar and battery project located in Coconino County, Arizona. The project, located in the Western region, consists of 750 MW of solar capacity. It is being developed within the Arizona Public Service (APS) interconnection queue, with a queue entry date of September 30, 2019. The proposed commercial operation date is June 30, 2023.

The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is the Moenkopi 500kV Substation.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Coconino

Grid Region

Mountain West

Market

Developer

Utility

Arizona Public Service

Entity

APS

Service Type

Point of Interconnection

Moenkopi 500kV Substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.