APS-Q317
750 MW hybrid in Coconino, AZ · In queue since September 2019 · Proposed COD June 2023
750 MW
Capacity
1
Components
Solar
6y 8m
In Queue
Cluster Study
IA Status
COD target: 2023
Total Duration
3y 9m
Schedule
35 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-06-30
APS-Q317 is a proposed 750 MW hybrid solar and battery project located in Coconino County, Arizona. The project, located in the Western region, consists of 750 MW of solar capacity. It is being developed within the Arizona Public Service (APS) interconnection queue, with a queue entry date of September 30, 2019. The proposed commercial operation date is June 30, 2023.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is the Moenkopi 500kV Substation.
Generated from interconnection queue and public data sources
State
AZ
County
Coconino
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Moenkopi 500kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.