APS-Q335
360 MW generation in Yavapai, AZ · In queue since March 2020 · Proposed COD May 2023
360 MW
Capacity
1
Components
Solar
6y 2m
In Queue
Cluster Study
IA Status
COD target: 2023
Total Duration
3y 2m
Schedule
36 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-05-31
APS-Q335 is a proposed 360 MW solar generation project located in Yavapai County, Arizona. The project is in the Arizona Public Service (APS) interconnection queue, under queue ID APS-Q335, with an entry date of March 27, 2020. The proposed commercial operation date is May 31, 2023.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is the Yavapai 500kV Substation.
Generated from interconnection queue and public data sources
State
AZ
County
Yavapai
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Yavapai 500kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q335