APS-Q348
300 MW hybrid in Coconino, AZ · In queue since September 2020 · Proposed COD December 2024
300 MW
Capacity
1
Components
Solar
5y 8m
In Queue
Cluster Study
IA Status
COD target: 2024
Total Duration
4y 3m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-01
APS-Q348 is a proposed 300 MW hybrid solar and battery energy storage project located in Coconino County, Arizona. The project, interconnected with Arizona Public Service (APS), entered the APS interconnection queue on September 22, 2020, with a proposed commercial operation date of December 1, 2024. The project's interconnection status is currently in the Cluster Study phase.
The project consists of 300 MW of solar generation capacity. It is located in the western United States and interconnects at the Moenkopi El Dorado 500kV Line. The project has appeared in recent news coverage regarding renewable energy development in Arizona.
Generated from interconnection queue and public data sources
State
AZ
County
Coconino
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Moenkopi El Dorado 500kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q348