APS-Q350
300 MW hybrid in Yuma, AZ · In queue since September 2020 · Proposed COD August 2022
300 MW
Capacity
1
Components
Solar
5y 8m
In Queue
Construction
IA Status
COD target: 2022
Total Duration
1y 11m
Schedule
46 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-08-01
APS-Q350 is a proposed 300 MW hybrid solar and battery project located in Yuma County, Arizona. The development project consists of 300 MW of solar generation, coupled with battery storage. Interconnection is with Arizona Public Service (APS) at the Orchard 230kV point of interconnection.
The project is listed in the APS interconnection queue as of September 28, 2020, with a proposed commercial operation date of August 1, 2022. The project's interconnection agreement status is currently listed as "Construction".
Generated from interconnection queue and public data sources
State
AZ
County
Yuma
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Orchard 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q350