APS-Q352
345 MW hybrid in Navajo, AZ · In queue since September 2020 · Proposed COD November 2023
345 MW
Capacity
1
Components
Solar
5y 8m
In Queue
Cluster Study
IA Status
COD target: 2023
Total Duration
3y 2m
Schedule
30 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-11-30
APS-Q352 is a proposed 345 MW solar and battery hybrid project located in Navajo County, Arizona. The project, which appeared in the Arizona Public Service (APS) interconnection queue on September 28, 2020, consists of 345 MW of solar capacity. Its proposed commercial operation date is November 30, 2023.
The project is currently in the Cluster Study phase of the interconnection process within the APS queue. The point of interconnection is the Cholla 345kV substation.
Generated from interconnection queue and public data sources
State
AZ
County
Navajo
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Cholla 345kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q352