APS-Q358
100 MW storage in Maricopa, AZ · In queue since September 2020 · Proposed COD December 2024
100 MW
Capacity
1
Components
Battery
5y 8m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
4y 3m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2024-12-31
APS-Q358 is a proposed 100 MW battery storage project located in Maricopa County, Arizona. The project is interconnected with Arizona Public Service (APS) and entered the APS interconnection queue on September 30, 2020. The proposed commercial operation date is December 31, 2024, and the Interconnection Agreement (IA) has been executed.
The development project consists of a 100 MW battery component. The point of interconnection (POI) is the Colter 69kV substation.
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Colter 69kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q358