APS-Q359
315 MW hybrid in Pinal, AZ · In queue since September 2020 · Proposed COD December 2023
315 MW
Capacity
1
Components
Solar
5y 8m
In Queue
Cluster Study
IA Status
COD target: 2023
Total Duration
3y 3m
Schedule
29 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-01
APS-Q359 is a proposed 315 MW hybrid solar and battery project located in Pinal County, Arizona. The development project consists of 315 MW of solar capacity. It is interconnected to the Arizona Public Service (APS) grid at the Milligan 230kV substation.
The project is listed in the APS interconnection queue with an entry date of September 30, 2020. The proposed commercial operation date is December 1, 2023. Its interconnection status is currently in the Cluster Study phase.
Generated from interconnection queue and public data sources
State
AZ
County
Pinal
Grid Region
Mountain West
Market
—
Developer
—
Utility
Arizona Public Service
Entity
APS
Service Type
—
Point of Interconnection
Milligan 230kV substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project APS-Q359